Construction Projects in 2021

Share on Facebook Share on Twitter Share on Linkedin Email this link

2021 construction has concluded

The City of Spruce Grove is gearing up for another busy construction year that will include many new projects, as well as the completion of multi-phased projects started in previous years. These projects will enhance the City’s roadways, utilities, buildings, parks and facilities.

This site has been created to help keeping the residents and businesses of Spruce Grove informed and aware of any and all impacts these projects may have on day to day life. We know that construction can impact residents and businesses and we thank you for your patience while we complete this work.

The City of Spruce Grove is gearing up for another busy construction year that will include many new projects, as well as the completion of multi-phased projects started in previous years. These projects will enhance the City’s roadways, utilities, buildings, parks and facilities.

This site has been created to help keeping the residents and businesses of Spruce Grove informed and aware of any and all impacts these projects may have on day to day life. We know that construction can impact residents and businesses and we thank you for your patience while we complete this work.

2021 construction has concluded

  • Construction project update - October 27, 2021

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    In progress

    Fairway Drive Culvert Replacement

    • Anticipated Start date: October 4th
    • Current location: Fairway Drive
    • Current activity: Culvert replacement
    • Anticipated completion: November 15th
    • Impacts: No thru traffic on Fairway Drive starting October 4th - November 15th
    • Fairway Drive closure October 4th - November 15th (No thru traffic)


    Watermain/Sanitary Rehab – Grove Meadows Neighbourhood (view overall project map)

    • Anticipated start date: Clean up currently in progress.
    • Current location: N/A
    • Current activity: Project complete; clean up in progress.
    • Anticipated completion: November 15th
    • Impacts: None.


    Complete

    Watermain and Surface Rehab – South Avenue (view overall project map)

    • Anticipated start date: Complete
    • Current location: N/A
    • Current activity: N/A
    • Anticipated completion: Complete
    • Impacts: N/A


    Industrial Storm Upgrades (view overall project map)

    • Anticipated start date: Complete
    • Current location: N/A
    • Current activity: N/A
    • Anticipated completion: Complete
    • Impacts: N/A


    Surface Improvements - Lakewood Neighbourhood (view overall project map)

    • Anticipated start date: Complete
    • Current location: N/A
    • Current activity: N/A
    • Anticipated completion: Complete
    • Impacts: N/A


    Surface Improvements – Grove Meadows Neighbourhood (view overall project map)

    • Anticipated start date: Completed
    • Current location: N/A
    • Current activity: Clean Up
    • Anticipated completion: Completed
    • Impacts: N/A
  • Temporary Jubilee Park trail closure

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Starting on October 15, 2021 construction of boardwalks will begin in the treed area on the north end of Jubilee Park. All access to the trails within this treed area will be closed to the public from November 1st through to November 26th. Residents are asked to stay away as this will be an active construction area.

  • Construction projects update - September 30, 2021

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    In progress

    Fairway Drive Culvert Replacement

    • Anticipated Start date: October 4th
    • Current location: Fairway Drive
    • Current activity: Culvert replacement
    • Anticipated completion: October 31st
    • Impacts: No thru traffic on Fairway Drive starting October 4th - 31st
    • Fairway Drive closure October 4th - October 31st (No thru traffic)


    Watermain/Sanitary Rehab – Grove Meadows Neighbourhood (view overall project map)

    • Anticipated start date: Currently in progress.
    • Current location: Greenwood Drive east of Goebel Drive
    • Current activity: CC replacement and mainline watermain replacement
    • Anticipated completion: October 10th
    • Impacts: No on street parking and limited street front access
    • Current rolling road closure on Greenwood Drive east of Greystone Drive


    Watermain and Surface Rehab – South Avenue (view overall project map)

    • Anticipated start date: Currently in progress.
    • Current location: South Avenue
    • Current activity: Asphalt re-surfacing
    • Anticipated completion: October 15th
    • Impacts: None.


    Complete

    Industrial Storm Upgrades (view overall project map)

    • Anticipated start date: Complete
    • Current location: N/A
    • Current activity: N/A
    • Anticipated completion: Complete
    • Impacts: N/A


    Surface Improvements - Lakewood Neighbourhood (view overall project map)

    • Anticipated start date: Complete
    • Current location: N/A
    • Current activity: N/A
    • Anticipated completion: Complete
    • Impacts: N/A


    Surface Improvements – Grove Meadows Neighbourhood (view overall project map)

    • Anticipated start date: Completed
    • Current location: N/A
    • Current activity: Clean Up
    • Anticipated completion: Completed
    • Impacts: N/A
  • Construction projects update - August 19, 2021

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    In progress

    Watermain/Sanitary Rehab – Grove Meadows Neighbourhood (view overall project map)

    • Anticipated start date: Currently in progress.
    • Current location: Greenwood Drive east of Greystone
    • Current activity: CC replacement and mainline watermain replacement
    • Anticipated completion: October 29th
    • Impacts: No on street parking and limited street front access
    • Current rolling road closure on Greenwood Drive east of Greystone Drive


    Watermain and Surface Rehab – South Avenue (view overall project map)

    • Anticipated start date: Currently in progress.
    • Current location: South Avenue
    • Current activity: Hydrant installations
    • Anticipated completion: October 29th
    • Impacts: Limited parking at ball diamonds. No parking on South Avenue.
    • Bulk Water Station will be closed starting July 12 for approximately 6 weeks.


    Industrial Storm Upgrades (view overall project map)

    • Anticipated start date: Currently in progress.
    • Current location: City right of ways within private property
    • Current activity: Storm main installation
    • Anticipated completion: August 27th
    • Impacts: N/A


    Complete

    Surface Improvements - Lakewood Neighbourhood (view overall project map)

    • Anticipated start date: Complete
    • Current location: N/A
    • Current activity: N/A
    • Anticipated completion: Complete
    • Impacts: N/A

    Surface Improvements – Grove Meadows Neighbourhood (view overall project map)

    • Anticipated start date: Completed
    • Current location: N/A
    • Current activity: N/A
    • Anticipated completion: Completed August 17th
    • Impacts: N/A
  • Construction projects update - July 29, 2021

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    In progress

    Surface Improvements – Grove Meadows Neighbourhood (view overall project map)

    • Anticipated start date: Currently in progress
    • Current location: Goebel Drive, Goebel Bay, Goebel Place, Goebel Close, Groat Crescent, Groat Drive, Groat Place, Greystone Drive, Grove Meadows Drive
    • Current activity: Paving
    • Anticipated completion: August 6
    • Impacts: No on street parking and limited street front access
    • Grove Meadows Drive and Greystone Drive closure July 29-30; Local Traffic Only


    Surface Improvements - Lakewood Neighbourhood (view overall project map)

    • Anticipated start date: June 25
    • Current location: Lakeland Drive and Lindsay Avenue
    • Current activity: Road reconstruction
    • Anticipated completion: October 1
    • Impacts: No on street parking and limited street front access.
    • Starting July 19 limited to local traffic only. Bus has been re-routed to Lakewood Drive and Lawson Blvd starting August 3.


    Watermain/Sanitary Rehab – Grove Meadows Neighbourhood (view overall project map)

    • Anticipated start date: Currently in progress.
    • Current location: Greystone Drive
    • Current activity: CC replacement and mainline watermain replacement
    • Anticipated completion: October 29
    • Impacts: No on street parking and limited street front access
    • Starting July 6, Greystone Drive closure. Anticipated completion August 9.


    Watermain and Surface Rehab – South Avenue (view overall project map)

    • Anticipated start date: Currently in progress.
    • Current location: South Avenue
    • Current activity: Mainline and hydrant installation
    • Anticipated completion: October 29
    • Impacts: Limited parking at ball diamonds. No parking on South Avenue.
    • Bulk Water Station will be closed starting July 12 for approximately 6 weeks.


    Industrial Storm Upgrades (view overall project map)

    • Anticipated start date: Currently in progress.
    • Current location: City right of ways within private property
    • Current activity: Storm main installation
    • Anticipated completion: August 27
    • Impacts: N/A


    Complete

  • Main Street closure - July 26-29

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Main Street, between First Avenue and McLeod Avenue, is expected to be closed to traffic from July 26 to July 29. Traffic control and detour signage will be in place. Local traffic will still have access (ex: for deliveries). This closure is part of the Columbus Park redevelopment project.

  • Century Road closure - July 13

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Century Road will closed northbound and southbound at the CN rail crossing on July 13, 2021 from 6 a.m. to 11 p.m. for repairs and upgrading.

    CN will have electronic signage eastbound and westbound on Highway 16A and northbound and southbound on Century Road starting July 9 advertising this upcoming closure.

  • Temporary closure of Bulk Water Station

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Starting on July 12, 2021, the City of Spruce Grove will be temporarily closing the Bulk Water Station / Truck Fill located on South Avenue. If you are a current user of the station we ask that you find alternative sources of water available through surrounding municipalities or private contractor. This work is expected to take six weeks to complete (weather dependent). Once work is complete, the station will be open and fully operational. The City will post any and all updates.

    We apologize for any inconvenience this may cause.

  • Construction projects update - June 28, 2021

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    In progress

    Surface Improvements – Grove Meadows Neighbourhood (view overall project map)

    • Anticipated start date: Currently in progress
    • Current location: Greystone Drive and Groat Drive
    • Current activity: Concrete replacement
    • Anticipated completion: August 27
    • Impacts: No on street parking and limited street front access


    Surface Improvements - Lakewood Neighbourhood (view overall project map)

    • Anticipated start date: June 25
    • Current location: Lakeland Drive
    • Current activity: Concrete replacement
    • Anticipated completion: October 1
    • Impacts: No on street parking and limited street front access. Starting July 12; limited to local traffic only.


    Watermain/Sanitary Rehab – Grove Meadows Neighbourhood (view overall project map)

    • Anticipated start date: Currently in progress.
    • Current location: Greenwood Drive, working west and Greystone Bay
    • Current activity: CC Replacement and Mainline Watermain replacement
    • Anticipated completion: October 29
    • Impacts: No on street parking and limited street front access
    • Starting July 6, Greystone Drive closure. Anticipated completion August 3.


    Watermain and Surface Rehab – South Avenue (view overall project map)

    • Anticipated start date: Currently in progress.
    • Current location: South Avenue
    • Current activity: Pipe fusing / Mainline installation
    • Anticipated completion: October 29
    • Impacts: Limited parking at ball diamonds. No parking on South Avenue.


    Industrial Storm Upgrades (view overall project map)

    • Anticipated start date: Currently in progress.
    • Current location: Alberta Avenue.
    • Current activity: Culvert replacement.
    • Anticipated completion: August 27
    • Impacts: N/A


    Coming soon

    Arterial Surface Improvements

    • Anticipated start date: July 5
    • Current location: N/A
    • Current activity: N/A
    • Anticipated completion: July 25
    • Impacts: N/A


    Arterial Resurfacing - Grove Drive (view overall project map)

    • Anticipated Start date: July 5, 2021
    • Current location: Grove Drive, eastbound from Jennifer Heil Way to Century Road and westbound from Calahoo Road to Jennifer Heil Way
    • Current activity: Mill asphalt and overlay with new asphalt.
    • Anticipated completion: July 25
    • Impacts: Traffic disruption throughout duration of the project. This work will be done at night to minimize disruption.


  • Construction projects update - May 13, 2021

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Several construction projects are underway in the city, while others will be starting in a few weeks. Please see below for updates.

    In progress

    Surface Improvements – Grove Meadows Neighbourhood (view overall project map)

    • Anticipated start date: May 10 (started)
    • Current location: Goebel Drive and Greystone Drive working east
    • Current activity: Concrete replacement
    • Anticipated completion: August 27
    • Impacts: No on street parking and limited street front access


    Watermain/Sanitary Rehab – Grove Meadows Neighbourhood (view overall project map)

    • Anticipated start date: May 10 (started)
    • Current location: Greystone Drive and Greenwood Drive working west
    • Current activity: Installation of temporary water servicing to homes
    • Anticipated completion: October 29
    • Impacts: No on street parking and limited street front access


    Coming soon

    Watermain and Surface Rehab – South Avenue (view overall project map)

    • Anticipated start date: May 25 (delayed from the original anticipated date)
    • Current location: South Avenue
    • Current activity: Line locating
    • Anticipated completion: October 29
    • Impacts: N/A at this time


    Industrial Storm Upgrades (view overall project map)

    • Anticipated start date: May 25 (delayed from the original anticipated date)
    • Current location: N/A
    • Current activity: N/A
    • Anticipated completion: August 27
    • Impacts: N/A