Construction projects update - May 13, 2021
Several construction projects are underway in the city, while others will be starting in a few weeks. Please see below for updates.
In progress
Surface Improvements – Grove Meadows Neighbourhood (view overall project map)
- Anticipated start date: May 10 (started)
- Current location: Goebel Drive and Greystone Drive working east
- Current activity: Concrete replacement
- Anticipated completion: August 27
- Impacts: No on street parking and limited street front access
Watermain/Sanitary Rehab – Grove Meadows Neighbourhood (view overall project map)
- Anticipated start date: May 10 (started)
- Current location: Greystone Drive and Greenwood Drive working west
- Current activity: Installation of temporary water servicing to homes
- Anticipated completion: October 29
- Impacts: No on street parking and limited street front access
Coming soon
Watermain and Surface Rehab – South Avenue (view overall project map)
- Anticipated start date: May 25 (delayed from the original anticipated date)
- Current location: South Avenue
- Current activity: Line locating
- Anticipated completion: October 29
- Impacts: N/A at this time
Industrial Storm Upgrades (view overall project map)
- Anticipated start date: May 25 (delayed from the original anticipated date)
- Current location: N/A
- Current activity: N/A
- Anticipated completion: August 27
- Impacts: N/A
Share Construction projects update - May 13, 2021 on Facebook
Share Construction projects update - May 13, 2021 on Twitter
Share Construction projects update - May 13, 2021 on Linkedin
Email Construction projects update - May 13, 2021 link
2021 construction has concluded