Construction projects update - May 13, 2021

Several construction projects are underway in the city, while others will be starting in a few weeks. Please see below for updates.

In progress

Surface Improvements – Grove Meadows Neighbourhood (view overall project map)

  • Anticipated start date: May 10 (started)
  • Current location: Goebel Drive and Greystone Drive working east
  • Current activity: Concrete replacement
  • Anticipated completion: August 27
  • Impacts: No on street parking and limited street front access


Watermain/Sanitary Rehab – Grove Meadows Neighbourhood (view overall project map)

  • Anticipated start date: May 10 (started)
  • Current location: Greystone Drive and Greenwood Drive working west
  • Current activity: Installation of temporary water servicing to homes
  • Anticipated completion: October 29
  • Impacts: No on street parking and limited street front access


Coming soon

Watermain and Surface Rehab – South Avenue (view overall project map)

  • Anticipated start date: May 25 (delayed from the original anticipated date)
  • Current location: South Avenue
  • Current activity: Line locating
  • Anticipated completion: October 29
  • Impacts: N/A at this time


Industrial Storm Upgrades (view overall project map)

  • Anticipated start date: May 25 (delayed from the original anticipated date)
  • Current location: N/A
  • Current activity: N/A
  • Anticipated completion: August 27
  • Impacts: N/A
Share Construction projects update - May 13, 2021 on Facebook Share Construction projects update - May 13, 2021 on Twitter Share Construction projects update - May 13, 2021 on Linkedin Email Construction projects update - May 13, 2021 link

2021 construction has concluded

<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>