Construction projects update - June 28, 2021
In progress
Surface Improvements – Grove Meadows Neighbourhood (view overall project map)
- Anticipated start date: Currently in progress
- Current location: Greystone Drive and Groat Drive
- Current activity: Concrete replacement
- Anticipated completion: August 27
- Impacts: No on street parking and limited street front access
Surface Improvements - Lakewood Neighbourhood (view overall project map)
- Anticipated start date: June 25
- Current location: Lakeland Drive
- Current activity: Concrete replacement
- Anticipated completion: October 1
- Impacts: No on street parking and limited street front access. Starting July 12; limited to local traffic only.
Watermain/Sanitary Rehab – Grove Meadows Neighbourhood (view overall project map)
- Anticipated start date: Currently in progress.
- Current location: Greenwood Drive, working west and Greystone Bay
- Current activity: CC Replacement and Mainline Watermain replacement
- Anticipated completion: October 29
- Impacts: No on street parking and limited street front access
- Starting July 6, Greystone Drive closure. Anticipated completion August 3.
Watermain and Surface Rehab – South Avenue (view overall project map)
- Anticipated start date: Currently in progress.
- Current location: South Avenue
- Current activity: Pipe fusing / Mainline installation
- Anticipated completion: October 29
- Impacts: Limited parking at ball diamonds. No parking on South Avenue.
Industrial Storm Upgrades (view overall project map)
- Anticipated start date: Currently in progress.
- Current location: Alberta Avenue.
- Current activity: Culvert replacement.
- Anticipated completion: August 27
- Impacts: N/A
Coming soon
Arterial Surface Improvements
- Anticipated start date: July 5
- Current location: N/A
- Current activity: N/A
- Anticipated completion: July 25
- Impacts: N/A
Arterial Resurfacing - Grove Drive (view overall project map)
- Anticipated Start date: July 5, 2021
- Current location: Grove Drive, eastbound from Jennifer Heil Way to Century Road and westbound from Calahoo Road to Jennifer Heil Way
- Current activity: Mill asphalt and overlay with new asphalt.
- Anticipated completion: July 25
- Impacts: Traffic disruption throughout duration of the project. This work will be done at night to minimize disruption.
Share Construction projects update - June 28, 2021 on Facebook
Share Construction projects update - June 28, 2021 on Twitter
Share Construction projects update - June 28, 2021 on Linkedin
Email Construction projects update - June 28, 2021 link
2021 construction has concluded