Construction projects update - July 29, 2021
In progress
Surface Improvements – Grove Meadows Neighbourhood (view overall project map)
- Anticipated start date: Currently in progress
 - Current location: Goebel Drive, Goebel Bay, Goebel Place, Goebel Close, Groat Crescent, Groat Drive, Groat Place, Greystone Drive, Grove Meadows Drive
 - Current activity: Paving
 - Anticipated completion: August 6
 - Impacts: No on street parking and limited street front access
 - Grove Meadows Drive and Greystone Drive closure July 29-30; Local Traffic Only
 
Surface Improvements - Lakewood Neighbourhood (view overall project map)
- Anticipated start date: June 25
 - Current location: Lakeland Drive and Lindsay Avenue
 - Current activity: Road reconstruction
 - Anticipated completion: October 1
 - Impacts: No on street parking and limited street front access.
 - Starting July 19 limited to local traffic only. Bus has been re-routed to Lakewood Drive and Lawson Blvd starting August 3.
 
Watermain/Sanitary Rehab – Grove Meadows Neighbourhood (view overall project map)
- Anticipated start date: Currently in progress.
 - Current location: Greystone Drive
 - Current activity: CC replacement and mainline watermain replacement
 - Anticipated completion: October 29
 - Impacts: No on street parking and limited street front access
 - Starting July 6, Greystone Drive closure. Anticipated completion August 9.
 
Watermain and Surface Rehab – South Avenue (view overall project map)
- Anticipated start date: Currently in progress.
 - Current location: South Avenue
 - Current activity: Mainline and hydrant installation
 - Anticipated completion: October 29
 - Impacts: Limited parking at ball diamonds. No parking on South Avenue.
 - Bulk Water Station will be closed starting July 12 for approximately 6 weeks.
 
Industrial Storm Upgrades (view overall project map)
- Anticipated start date: Currently in progress.
 - Current location: City right of ways within private property
 - Current activity: Storm main installation
 - Anticipated completion: August 27
 - Impacts: N/A
 
Complete
- Arterial Surface Improvements
 - Arterial Resurfacing - Grove Drive (view overall project map)
 
Share Construction projects update - July 29, 2021 on Facebook
Share Construction projects update - July 29, 2021 on Twitter
Share Construction projects update - July 29, 2021 on Linkedin
Email Construction projects update - July 29, 2021 link
2021 construction has concluded