Construction project update - October 27, 2021
In progress
Fairway Drive Culvert Replacement
- Anticipated Start date: October 4th
- Current location: Fairway Drive
- Current activity: Culvert replacement
- Anticipated completion: November 15th
- Impacts: No thru traffic on Fairway Drive starting October 4th - November 15th
- Fairway Drive closure October 4th - November 15th (No thru traffic)
Watermain/Sanitary Rehab – Grove Meadows Neighbourhood (view overall project map)
- Anticipated start date: Clean up currently in progress.
- Current location: N/A
- Current activity: Project complete; clean up in progress.
- Anticipated completion: November 15th
- Impacts: None.
Complete
Watermain and Surface Rehab – South Avenue (view overall project map)
- Anticipated start date: Complete
- Current location: N/A
- Current activity: N/A
- Anticipated completion: Complete
- Impacts: N/A
Industrial Storm Upgrades (view overall project map)
- Anticipated start date: Complete
- Current location: N/A
- Current activity: N/A
- Anticipated completion: Complete
- Impacts: N/A
Surface Improvements - Lakewood Neighbourhood (view overall project map)
- Anticipated start date: Complete
- Current location: N/A
- Current activity: N/A
- Anticipated completion: Complete
- Impacts: N/A
Surface Improvements – Grove Meadows Neighbourhood (view overall project map)
- Anticipated start date: Completed
- Current location: N/A
- Current activity: Clean Up
- Anticipated completion: Completed
- Impacts: N/A
Share Construction project update - October 27, 2021 on Facebook
Share Construction project update - October 27, 2021 on Twitter
Share Construction project update - October 27, 2021 on Linkedin
Email Construction project update - October 27, 2021 link
2021 construction has concluded