Construction Projects in 2023

Share Construction Projects in 2023 on Facebook Share Construction Projects in 2023 on Twitter Share Construction Projects in 2023 on Linkedin Email Construction Projects in 2023 link

2023 construction has concluded

The City of Spruce Grove is gearing up for another busy construction year that will include many new projects, as well as the completion of multi-phased projects started in previous years. These projects will enhance the City’s roadways, utilities, buildings, parks and facilities.

This site has been created to help keeping the residents and businesses of Spruce Grove informed and aware of any and all impacts these projects may have on day to day life. We know that construction can impact residents and businesses and we thank you for your patience while we complete this work.

The City of Spruce Grove is gearing up for another busy construction year that will include many new projects, as well as the completion of multi-phased projects started in previous years. These projects will enhance the City’s roadways, utilities, buildings, parks and facilities.

This site has been created to help keeping the residents and businesses of Spruce Grove informed and aware of any and all impacts these projects may have on day to day life. We know that construction can impact residents and businesses and we thank you for your patience while we complete this work.

2023 construction has concluded

  • Traffic signal work overnight at Century Road/Grove Drive intersection

    Share Traffic signal work overnight at Century Road/Grove Drive intersection on Facebook Share Traffic signal work overnight at Century Road/Grove Drive intersection on Twitter Share Traffic signal work overnight at Century Road/Grove Drive intersection on Linkedin Email Traffic signal work overnight at Century Road/Grove Drive intersection link

    UPDATE: This work has been rescheduled to the night of October 27, 2023.

    One evening this weekend (Friday, Saturday or Sunday) during overnight hours, crews will be working on the traffic signals at the Century Road and Grove Drive intersection. There will be one northbound lane closed and one southbound lane closed on Century Road to accommodate the work. At least one lane in each direction will be maintained at all times. Please look for and follow all signage and barricades.

  • Construction Projects Update - October 26, 2023

    Share Construction Projects Update - October 26, 2023 on Facebook Share Construction Projects Update - October 26, 2023 on Twitter Share Construction Projects Update - October 26, 2023 on Linkedin Email Construction Projects Update - October 26, 2023 link

    2023 City Center Watermain Rehabilitation

    This work is to replace the existing watermain within Golden Spike Road/Calahoo Road, from south of the CN Rail to Weston Drive.

    • All watermain work and surface restoration work is complete.

    Atco Gas Project – Diamond Avenue

    Diamond Avenue from Madison Crescent to Schram Street ; the work is to install a new gas main to reinforce service in the Industrial area.

    • All work by Atco Gas is complete

    2023 Surface Improvement Program

    • Jespersen Avenue – Road construction on Jespersen Avenue from King Street to Queen Street is complete.
    • Creekside Way – Resurfacing work at Creekside Way is complete.
    • Stoneshire Manor – Road Construction work at Stoneshire Manor is complete.

    2023 Deer Park Surface Rehabilitation

    Project includes concrete curb and gutter and sidewalk removal and replacement, as well as milling/paving of roads and pulverize/paving of roads.

    • All work is complete.

    2023 Highway 16A Resurfacing

    Project will include milling and paving at Hwy 16A eastbound from Jennifer Heil Way to Nelson Drive and Hwy 16A eastbound from Century Road to the east City limit, including entire Hwy 16A/Century Road intersection.

    • All work is complete.

    2023 Pioneer Road Top Lift Asphalt Construction

    Project includes prefilling and paving of Grove Drive from existing roundabout to approximately 180m west, and Pioneer Road from Grove Drive to Hwy 16A.

    • All work is complete.

    2023 Traffic Signal Rehab

    This project includes replacement of the traffic signals at the Calahoo Road/Millgrove Drive intersection and improvements to the traffic signals at the Grove Drive/King Street intersection.

    • All work is complete.

    2023 Greenbury Village Dewatering

    This project includes placement of storm sewer at the north end of the existing bio-swale, to encourage groundwater to drain to a washed rock and perforated pipe bed, lowering the water table in the immediate area. Monitoring of the groundwater levels, using existing monitoring wells, will continue through to September 2024.

    • All work is complete.

    2023 Pedestrian Walkways

    Sidewalk constructed from the existing crosswalk to Broxton Park School, to the existing bus pad west of the Church. New crosswalks, with road narrowing concrete slabs, paint, signage, and delineators constructed at the McLeod/Brebner, and McLeod/LaZerte intersections and at the existing crosswalk to the school.

    • All work is complete.

    2023 Industrial Watermain Rehab

    This project includes replacement and upsizing of watermains in the Industrial area of Spruce Grove. 2023 work is at Century Road from South Avenue to Diamond Avenue and then from Diamond Avenue from Century Road to Schram Street.

    • Work expected to be completed by October 31.

    2023 Pressure Reducing Valve Installation

    To accomodate installation of pressure reducing valves in various locations in the north part of Spruce Grove (Longview Drive - north of Kings Link, Fairway Point, Aspenglen Drive - south of Ashgrove Drive and Fieldstone - within green space). Road closures will be as follows:

    • Aspenglen Dr (PRV #6) -Completed and road is open.
    • Fairway Dr (PRV #8) - Completed and road is open.
    • Fieldstone Park (PRV #7) - Date: October 11 – 18. Completed and asphalt trail expected to be open to pedestrian traffic October 27
    • Longview Dr (PRV #9) - Date: October 18 – 26. Longview Drive will be open to traffic by end of day October 26. Longview Drive will be closed again to traffic on October 30 between 9am and 2pm for paving.

    2022/2023 Oversize Load Corridor

    Work has been completed at all traffic signals on the Campsite Road/Jennifer Heil Way corridor, to place adapters on the north/south poles allowing them to accommodate oversize loads through Spruce Grove. Fortis will be moving overhead lines at Diamond Avenue and Campsite Road, to underground to allow the oversize loads to use this route.

    • Work expected to be completed by November 30
  • Construction Projects Update - October 18, 2023

    Share Construction Projects Update - October 18, 2023 on Facebook Share Construction Projects Update - October 18, 2023 on Twitter Share Construction Projects Update - October 18, 2023 on Linkedin Email Construction Projects Update - October 18, 2023 link

    2023 City Center Watermain Rehabilitation

    This work is to replace the existing watermain within Golden Spike Road/Calahoo Road, from south of the CN Rail to Weston Drive.

    • All watermain work and surface restoration work is complete.

    Atco Gas Project – Diamond Avenue

    Diamond Avenue from Madison Crescent to Schram Street ; the work is to install a new gas main to reinforce service in the Industrial area.

    • All work by Atco Gas is complete

    2023 Surface Improvement Program

    • Jespersen Avenue – Road construction on Jespersen Avenue from King Street to Queen Street is complete.
    • Creekside Way – Resurfacing work at Creekside Way is complete.
    • Stoneshire Manor – Road Construction work at Stoneshire Manor is complete.

    2023 Deer Park Surface Rehabilitation

    Project includes concrete curb and gutter and sidewalk removal and replacement, as well as milling/paving of roads and pulverize/paving of roads.

    • All work is complete.

    2023 Highway 16A Resurfacing

    Project will include milling and paving at Hwy 16A eastbound from Jennifer Heil Way to Nelson Drive and Hwy 16A eastbound from Century Road to the east City limit, including entire Hwy 16A/Century Road intersection.

    • All work is complete.

    2023 Pioneer Road Top Lift Asphalt Construction

    Project includes prefilling and paving of Grove Drive from existing roundabout to approximately 180m west, and Pioneer Road from Grove Drive to Hwy 16A.

    • All work is complete.

    2023 Traffic Signal Rehab

    This project includes replacement of the traffic signals at the Calahoo Road/Millgrove Drive intersection and improvements to the traffic signals at the Grove Drive/King Street intersection.

    • All work is complete.

    2023 Industrial Watermain Rehab

    This project includes replacement and upsizing of watermains in the Industrial area of Spruce Grove. 2023 work is at Century Road from South Avenue to Diamond Avenue and then from Diamond Avenue from Century Road to Schram Street.

    • Work expected to be completed by October 27.

    Traffic Disruptions: Century Road, from Diamond Avenue to South Avenue will be closed September 29 - October 21. Detour is available by way of Yellowhead Road.

    2023 Pressure Reducing Valve Installation

    This project includes installation of pressure reducing valves in various locations in the north part of Spruce Grove (Longview Drive – north of King’s Link, Fairway Drive – south of Fairway Point, Aspenglen Drive - south of Ashgrove Drive and Fieldstone – within green space)

    • Completion Date: October 27
    • Aspenglen Dr (PRV #6) - Complete
    • Fairway Dr (PRV #8) – work expected to be completed by October 19
    • Fieldstone Park (PRV #7) - work expected to be completed by October 20
    • Longview Dr (PRV #9) – Work expected to be completed October 27. Longview Drive closed for construction north of King’s Link.

    2023 Greenbury Village Dewatering

    This project includes placement of storm sewer at the north end of the existing bio-swale, to encourage groundwater to drain to a washed rock and perforated pipe bed, lowering the water table in the immediate area. Monitoring of the groundwater levels, using existing monitoring wells, will continue through to September 2024.

    • All work is complete.

    2022/2023 Oversize Load Corridor

    Work has been completed at all traffic signals on the Campsite Road/Jennifer Heil Way corridor, to place adapters on the north/south poles allowing them to swivel out of the way to accommodate oversize loads through Spruce Grove. Fortis will be moving overhead lines at Diamond Avenue and Campsite Road, to underground to allow the oversize loads to use this route.

    • Work expected to be completed by November 30

    2023 Pedestrian Walkways

    Sidewalk constructed from the existing crosswalk to Broxton Park School, to the existing bus pad west of the Church. New crosswalks, with road narrowing concrete slabs, paint, signage, and delineators constructed at the McLeod/Brebner, and McLeod/LaZerte intersections and at the existing crosswalk to the school.

    • All work is complete.
  • 2023 Pressure Reducing Valve Installation - UPDATE

    Share 2023 Pressure Reducing Valve Installation - UPDATE on Facebook Share 2023 Pressure Reducing Valve Installation - UPDATE on Twitter Share 2023 Pressure Reducing Valve Installation - UPDATE on Linkedin Email 2023 Pressure Reducing Valve Installation - UPDATE link

    2023 Pressure Reducing Valve Installation

    This project includes installation of pressure reducing valves in various locations in the north part of Spruce Grove (Longview Drive – north of King’s Link, Fairway Drive – south of Fairway Point, Aspenglen Drive - south of Ashgrove Drive and Fieldstone – within green space)

    • Start Date: September 18
    • Completion Date: October 26
    • Traffic Disruptions: Where necessary, road closures with detours, will be in place. Appropriate traffic accommodations will be put in place including barricades, signs and flag persons as required.
    • Aspenglen Dr (PRV #6) -Completed and road is open.
    • Fairway Dr (PRV #8) - Fairway Drive closed south of Fairway Point September 25 – October 11
    • Fieldstone Park (PRV #7) - Date: October 11 – 18. Work expected within the green space north of Fieldstone Crescent and south of Linkside Court. The asphalt pedestrian walkway through this green space will be closed for the duration of the work.
    • Longview Dr (PRV #9) - Date: October 18 – 25
  • Construction Projects Update - September 28, 2023

    Share Construction Projects Update - September 28, 2023 on Facebook Share Construction Projects Update - September 28, 2023 on Twitter Share Construction Projects Update - September 28, 2023 on Linkedin Email Construction Projects Update - September 28, 2023 link

    2023 City Center Watermain Rehabilitation

    This work is to replace the existing watermain within Golden Spike Road/Calahoo Road, from south of the CN Rail to Weston Drive.

    • All watermain work is now complete. Surface work is ongoing and expected to be completed by September 30, at which time, Calahoo Road/Golden Spike Road will be fully opened to traffic.

    Atco Gas Project – Diamond Avenue

    Diamond Avenue from Madison Crescent to Schram Street ; the work is to install a new gas main to reinforce service in the Industrial area.

    • All work by Atco Gas is now complete

    2023 Surface Improvement Program

    • Jespersen Avenue – Road construction work is complete on Jespersen Avenue from King Street to Queen Street.
    • Creekside Way – Resurfacing work at Creekside Way is expected to be completed by October 6, 2023.
    • Stoneshire Manor – Road Construction work at Stoneshire Manor is complete.

    2023 Deer Park Surface Rehabilitation

    Project includes concrete curb and gutter and sidewalk removal and replacement, as well as milling/paving of roads and pulverize/paving of roads.

    • Expected completion date is October 12.

    2023 Highway 16A Resurfacing

    Project will include milling and paving at Hwy 16A eastbound from Jennifer Heil Way to Nelson Drive and Hwy 16A eastbound from Century Road to the east City limit, including entire Hwy 16A/Century Road intersection.

    • All work is now complete

    2023 Pioneer Road Top Lift Asphalt Construction

    Project includes prefilling and paving of Grove Drive from existing roundabout to approximately 180m west, and Pioneer Road from Grove Drive to Hwy 16A. Work will be completed at night and will immediately follow the work being done on Highway 16A. Traffic will be accommodated and appropriate signage. barricades and flag persons will be initiated as required.

    • All work is now complete

    2023 Traffic Signal Rehab

    This project includes replacement of the traffic signals at the Calahoo Road/Millgrove Drive intersection and improvements to the traffic signals at the Grove Drive/King Street intersection. New traffic signal installation at Calahoo Road/Millgrove Drive intersection is complete. Work at Grove Drive/King Street traffic signals to be complete September 7.

    • All work is now complete

    2023 Industrial Watermain Rehab - *UPDATE

    This project includes replacement and upsizing of watermains in the Industrial area of Spruce Grove. 2023 work is at Century Road from South Avenue to Diamond Avenue and then from Diamond Avenue from Century Road to Schram Street.

    • Start Date: June 27
    • Completion Date: October 21

    Traffic Disruptions: Century Road, from Diamond Avenue to South Avenue will be closed September 29 - October 21. Detour is available by way of Yellowhead Road.

    2023 Pressure Reducing Valve Installation

    This project includes installation of pressure reducing valves in various locations in the north part of Spruce Grove (Longview Drive – north of King’s Link, Fairway Drive – south of Fairway Point, Aspenglen Drive - south of Ashgrove Drive and Fieldstone – within green space)

    • Start Date: September 18
    • Completion Date: October 26
    • Traffic Disruptions: Where necessary, road closures with detours, will be in place. Appropriate traffic accommodations will be put in place including barricades, signs and flag persons as required.
    • Aspenglen Dr (PRV #6) - Aspenglen Drive closed between Ashgrove Drive and Aspenglen Place September 18 to October 3
    • Fairway Dr (PRV #8) - Fairway Drive closed south of Fairway Point September 28 to October 6
    • Fieldstone Park (PRV #7) - Date: TBD – There is not expected to be any impact to traffic.
    • Longview Dr (PRV #9) - Date: TBD

    2023 Greenbury Village Dewatering

    This project includes placement of storm sewer at the north end of the existing bioswale, to encourage groundwater to drain to a washed rock and perforated pipe bed, lowering the water table in the immediate area. Monitoring of the groundwater levels, using existing monitoring wells, will continue through to September 2024.

    • Work expected to be completed by September 29

    2022/2023 Oversize Load Corridor

    Work has been completed at all traffic signal on the Campsite Road/Jennifer Heil Way corridor, to place adapters on the north/south poles allowing them to swivel out of the way to accommodate oversize loads through Spruce Grove. Fortis will be moving overhead lines at Diamond Avenue and Campsite Road, to underground to allow the oversize loads to use this route.

    • Work expected to be completed by November 10

    2023 Pedestrian Walkways

    New sidewalk on the south side of McLeod Avenue from the existing crosswalk at the east end of Broxton Park School, to the existing bus pad west of Broxton Park School and 3 new crosswalks with concrete bump outs, signage and high visible yellow paint, crossing McLeod Avenue. These new crosswalks allow for safer crossing of McLeod Avenue due to the bump outs and narrowed roadway. These also encourage traffic calming in the immediate area.

    • All work is now complete.
  • 2023 Industrial Watermain Rehabilitation - Century Road *UPDATE*

    Share 2023 Industrial Watermain Rehabilitation - Century Road *UPDATE* on Facebook Share 2023 Industrial Watermain Rehabilitation - Century Road *UPDATE* on Twitter Share 2023 Industrial Watermain Rehabilitation - Century Road *UPDATE* on Linkedin Email 2023 Industrial Watermain Rehabilitation - Century Road *UPDATE* link

    Starting on or about September 29 until approximately the middle of October, a section of Century Road from South Avenue to Diamond Avenue will be temporarily closed to replace a section of the watermain.

    Motorists travelling on Century Road can follow the detour signs on site to Yellowhead Road in order to continue north or south.

    We apologize for any inconvenience this may cause and thank you for your patience.

  • Greenbury Village Dewatering Project

    Share Greenbury Village Dewatering Project on Facebook Share Greenbury Village Dewatering Project on Twitter Share Greenbury Village Dewatering Project on Linkedin Email Greenbury Village Dewatering Project link

    The Greenbury Village Dewatering project begins on Monday, September 25 and is expected to be completed by Saturday, September 30.

    Work will be happening at the north end of the bioswale at the Greenbury Blvd/Greenbury Manor/Gilmore Way intersection. A new catch basin will be installed at the north end of the bioswale and a perforated pipe wrapped in washed rock will be connected from the new catch basin to existing storm sewer to better drain the bioswale.

    There will be some minor traffic disruption but no road closures as the work happens.

  • Temporary full closure of Church Road and Main Street intersection starting September 27

    Share Temporary full closure of Church Road and Main Street intersection starting September 27 on Facebook Share Temporary full closure of Church Road and Main Street intersection starting September 27 on Twitter Share Temporary full closure of Church Road and Main Street intersection starting September 27 on Linkedin Email Temporary full closure of Church Road and Main Street intersection starting September 27 link

    Starting on or about September 27, there will be a temporary full closure at the intersection of Church Road and Main Street to accommodate the final paving of the area. This closure is expected to last approximately one week.

    Crosswalks around the intersection will remain open throughout the work. A few parking spots will be temporarily removed on each side during the closure to allow crews access to the area.

    Thank you for your patience during this temporary closure.

  • 2023 Pressure Reducing Valve Installation - Update September 20

    Share 2023 Pressure Reducing Valve Installation - Update September 20 on Facebook Share 2023 Pressure Reducing Valve Installation - Update September 20 on Twitter Share 2023 Pressure Reducing Valve Installation - Update September 20 on Linkedin Email 2023 Pressure Reducing Valve Installation - Update September 20 link
    supporting image

    This project includes the installation of Pressure Reducing Valves (PRV's) on four different locations in the City. The PRV's are to reduce high incoming water pressure and provide more functional water distribution along the north portion of the City.

    Streamline Construction will begin work on September 18th, through mid October tentatively. Roads will be sequentially closed during PRV installation, one location at a time. Signage and notices will be provided prior to the work commencing.

    See below for attached timelines and areas of road closure:

    Aspenglen Drive (PRV #6) - September 18 - 30


    Fairway Drive (PRV #8) - September 25 - Oct 7

    Fieldstone Park (PRV #7) - Date to be determined

    Longview Drive (PRV #9) - Date to be determined


  • Construction Projects Update - September 1, 2023

    Share Construction Projects Update - September 1, 2023 on Facebook Share Construction Projects Update - September 1, 2023 on Twitter Share Construction Projects Update - September 1, 2023 on Linkedin Email Construction Projects Update - September 1, 2023 link

    2023 City Center Watermain Rehabilitation

    This work is to replace the existing watermain within Golden Spike Road/Calahoo Road, from south of the CN Rail to Weston Drive.

      • Start Date: May 15
      • Completion Date: September 27

    Traffic disruptions: Through the duration of the project some sections of Golden Spike Road/Calahoo Road will be closed. Final phase of watermain construction is ongoing from Church Road to south of McLeod Avenue, within the southbound lanes of Calahoo Road.

    Atco Gas Project – Diamond Avenue

    • Diamond Avenue from Madison Crescent to Schram Street; The work is to install a new gas main to reinforce service in the Industrial area. Most of the work will be done by directional drilling, but there will be some locations where excavation is required. Work is complete from Madison Crescent to Golden Spike Road. Work continues from Golden Spike Road to Schram Street.
      • Start Date: May 11
      • Completion Date: September 15

    2023 Surface Improvement Program

    • Jespersen Avenue – Work is complete from King Street to east of Main Street. Road construction from Main Street to Queen Street continues and is expected to be complete by September 15. Line Painting and landscaping work may continue.
    • Creekside Way; full depth pulverizing/paving.
      • Start Date: September 7
      • Completion Date: September 22
    • Stoneshire Manor; concrete repairs and mill/pave.
      • Start Date: August 8
      • Completion Date: September 9

    2023 Deer Park Surface Rehabilitation

    Project includes concrete curb and gutter and sidewalk removal and replacement, as well as milling/paving of roads and pulverize/paving of roads.

      • Start Date: July 25
      • Completion Date: September 30
    • Traffic Disruptions: Appropriate traffic accommodations will be put in place including barricades, signs and flag person where required.

    2023 Highway 16A Resurfacing

    Project will include milling and paving at:

    • Hwy 16A eastbound from Jennifer Heil Way to Nelson Drive.
    • Hwy 16A eastbound from Century Road to the east City limit, including full Hwy 16A/Century Road intersection.
      • Start Date: July 23
      • Completion Date: COMPLETE

    2023 Pioneer Road Top Lift Asphalt Construction

    • Project includes prefilling and paving of Grove Drive from existing roundabout to approximately 180m west and Pioneer Road from Grove Drive to Hwy 16A. Work will be completed at night and will immediately follow the work being done on Highway 16A. Traffic will be accommodated and appropriate signage. barricades and flag persons will be initiated as required.
      • Start Date: Immediately following work on Hwy 16A – Early August
      • Completion Date: COMPLETE

    2023 Traffic Signal Rehab

    This project includes replacement of the traffic signals at the Calahoo Road/Millgrove Drive intersection and improvements to the traffic signals at the Grove Drive/King Street intersection. New traffic signal installation at Calahoo Road/Millgrove Drive intersection is complete. Work at Grove Drive/King Street traffic signals to be complete September 7

    • Start Date: July 5
    • Completion Date: September 7

    2023 Industrial Watermain Rehab

    This project includes replacement and upsizing of watermains in the Industrial area of Spruce Grove. 2023 work is at Century Road from South Avenue to Diamond Avenue and then from Diamond Avenue from Century Road to Schram Street.

    • Start Date: June 27
    • Completion Date: September 30
    • Traffic Disruptions: Road will be narrow and two direction traffic will be maintained. At times, short road closures will be necessary and detours will be in place. Appropriate traffic accommodations will be put in place including barricades, signs and flag persons as required.

    2023 Pressure Reducing Valve Installation

    This project includes installation of concrete chambers with valves to control water pressures in various locations in Spruce Grove (Longview Drive – north of King’s Link, Fairway Drive – south of Fairway Point, Aspenglen Drive - south of Ashgrove Drive and Fieldstone – within green space)

    • Start Date: September 18
    • Completion Date: October 20
    • Traffic Disruptions: Where necessary, road closures up to 7 days will be necessary and detours will be in place. Appropriate traffic accommodations will be put in place including barricades, signs and flag persons as required.