Form work for the pump track begins
The future wheeled sports park is beginning to take shape! Crews have been hard at work preparing the site for the first concrete pour which is expected to happen later this fall. Here's a snapshot of the progress we made in July and August:
- New water and stormwater utilities were installed.
- New clay fill material was brought in and compacted for the future skate park, pump track, bike skills park, and playground.
- Installation of formwork for concrete on the pump track is underway.