Construction Projects Update - July 17, 2023

2023 City Center Watermain Rehabilitation

This work is to replace the existing watermain within Golden Spike Road/Calahoo Road, from south of the CN Rail to Weston Drive.

    • Start Date: May 15th
    • Completion Date: Mid-August
  • Traffic disruptions: At different locations, throughout the duration of the project some sections of Golden Spike Road/Calahoo Road will be closed. Currently First Avenue is closed at Calahoo Road as part of a traffic accomodation and safety plan; in place to complete watermain work between the CN Rail and McLeod Avenue.


Atco Gas Project – Diamond Avenue

  • Diamond Avenue from Madison Crescent to Schram Street; The work is to install a new gas main to reinforce service in the Industrial area. Most of the work will be done by directional drilling, but there will be some locations where excavation is required.
    • Start Date: May 11, 2023
    • Completion Date: Mid-August.


2023 Surface Improvement Program

  • Jespersen Avenue; concrete repairs and full depth pulverizing/paving at Jespersen Avenue from King Street to Queen Street.
    • Start Date: June 12th
    • Completion Date: August 31st
  • Creekside Way; full depth pulverizing/paving.
    • Start Date: August 14th
    • Completion Date: August 30th
  • Stoneshire Manor; concrete repairs and mill/pave.
    • Start Date: mid-August
    • Completion Date: end of August

2023 Deer Park Surface Rehabilitation

This project will include concrete curb and gutter and sidewalk removal and replacement, as well as milling and paving of roads.

    • Start Date: Mid-July
    • Completion Date: end of August
  • Traffic Disruptions: Appropriate traffic accommodations will be put in place including barricades, signs and flag person where required.


2023 Highway 16A Resurfacing

This project will include milling and paving at the locations stated below: Eastbound from Jennifer Heil Way to Nelson Drive.

  • Hwy 16A eastbound from Jennifer Heil Way to Nelson Drive.
  • Hwy 16A eastbound from Century Road to the east City limit, including Hwy 16A/Century Road intersection.
    • Start Date: July 23rd
    • Completion Date: August 4th
  • Traffic Disruptions: Work will be completed at night. During the day, traffic will be split on the westbound lanes. Appropriate traffic accommodations will be put in place including barricades, signs and flag person as required.


2023 Pioneer Road Top Lift Asphalt Construction

This project prefilling and paving of the locations below. Work will be completed at night and will immediately follow the work being done on Highway 16A. Traffic will be accommodated and appropriate signage. barricades and flag persons will be initiated as required.

  • Grove Drive from existing round-a-bout to approximately 180m west.
  • Pioneer Road from Grove Drive to Hwy 16A (approximately 180m west of the intersection roundabout)Start Date: immediately following work on Hwy 16A, late July
    • Start Date: immediately following work on Hwy 16A, Early August.
    • Completion Date: Mid August
  • Traffic Disruptions: During construction, traffic will be split on the westbound lanes. Appropriate traffic accommodations will be put in place including barricades, signs and flag persons as required.


2023 Industrial Watermain Rehab

This project includes replacement and upsizing of watermains in the Industrial area of Spruce Grove. 2023 work is at Century Road from South Avenue to Diamond Avenue and then from Diamond Avenue from Century Road to Schram Street.

  • Start Date: June 27, 2023
  • Completion Date: October 15th
  • Traffic Disruptions: Road will be narrow and two direction traffic will be maintained. Appropriate traffic accomodations will be put in place including barricades, signs and flag persons as required.



*Please remember to refer to "Current Road Closures" on this site for up-to-date closure notifications.

Share Construction Projects Update - July 17, 2023 on Facebook Share Construction Projects Update - July 17, 2023 on Twitter Share Construction Projects Update - July 17, 2023 on Linkedin Email Construction Projects Update - July 17, 2023 link

2023 construction has concluded

<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>