Construction Projects Update June 2022
2022 Paving & Surface
-
Grove Meadows
- Construction is underway; concrete replacement is complete. Road re-surfacing is scheduled to begin July 4th - 9th weather dependent.
-
Lakewood
- Construction is underway; concrete replacement is currently being completed and road re-surfacing is scheduled to begin mid-July.
*Please remember to watch for No Parking signs; watch and stay clear of construction vehicles.
2022 Underground Replacement
-
Jespersen Avenue
- Mainline construction is complete.
- Concrete replacement and trench patching is scheduled for week of July11th weather dependent.
-
Storm Sewer Upgrades
- Completion of the Fairways Drive culvert replacement and various catch basin replacements throughout the City. Start Date July 11th
*Please refer to "Current Road Closures" on this site for closure notifications.
Share Construction Projects Update June 2022 on Facebook
Share Construction Projects Update June 2022 on Twitter
Share Construction Projects Update June 2022 on Linkedin
Email Construction Projects Update June 2022 link