Construction Projects Update June 2022

2022 Paving & Surface

  • Grove Meadows
    • Construction is underway; concrete replacement is complete. Road re-surfacing is scheduled to begin July 4th - 9th weather dependent.
  • Lakewood
    • Construction is underway; concrete replacement is currently being completed and road re-surfacing is scheduled to begin mid-July.

*Please remember to watch for No Parking signs; watch and stay clear of construction vehicles.


2022 Underground Replacement

  • Jespersen Avenue
    • Mainline construction is complete.
    • Concrete replacement and trench patching is scheduled for week of July11th weather dependent.
  • Storm Sewer Upgrades
    • Completion of the Fairways Drive culvert replacement and various catch basin replacements throughout the City. Start Date July 11th

*Please refer to "Current Road Closures" on this site for closure notifications.