City Centre redevelopment plans for 2025
Following three years of significant construction in the City Centre area, the focus of work for the 2025 construction season will be on watermain and sanitary sewer rehabilitation, as well as surface rehabilitation.
Mohr Avenue watermain and sanitary sewer rehabilitation
Starting April 14 and continuing until the last week of June, the remaining water mainline and sanitary sewer mainline rehabilitation work from 2024 will be conducted along Mohr Avenue, Spruce Glen (East) to Queen Street. Temporary water will be provided to affected residents for the duration of the construction.
Traffic disruptions, including phased road closures, should be expected in the area.
Mohr Avenue surface rehabilitation
Surface rehabilitation from Calahoo Road to Main Street will begin after underground work has been completed. Construction is anticipated to start the first week of July and be ongoing until the last week of September.
Traffic disruptions are expected in the area.
First Avenue alley watermain and sanitary rehabilitation
Alley watermain and sanitary sewer rehabilitation construction is anticipated to start the first week of June and will be ongoing through August along First Avenue. Temporary water will be provided to affected residents for the duration of the construction.
Traffic disruption including alley closures should be expected, and detours will be in place at times during construction. Access to businesses will be maintained as best as possible.
Golden Spike Road resurfacing
Road resurfacing on Golden Spike Road from Highway 16A to Railway Avenue is scheduled to start mid- to late-May and is anticipated to be completed mid-June.
During 2025 City Centre area improvements, businesses and local patrons should expect temporary traffic disruptions. More information will be shared here, and you can stay informed by subscribing for project updates.
Thank you for your patience this construction season as work continues to revitalize our City Centre.